About to start construction of 8 high-voltage power projects
The Southern Power Projects Management Board said that the unit is preparing to start construction of eight more high-voltage power projects in Dong Nai province.
Specifically, from the fourth quarter of 2022 to the fourth quarter of 2023, will in turn deploy projects of 220kV, 500kV transmission lines and transformer stations in districts: Long Thanh, Nhon Trach, Cam My.
In which there are 2 projects of lines connecting to Nhon Trach 3 Power Plant and Nhon Trach 4 Power Plant to transmit thermal power to these plants.; Dong Nai 2 500kV transformer station and connecting lines to supplement power load capacity in Dong Nai and surrounding areas.
The Southern Power Projects Management Board recommends that leaders at all levels pay attention to site clearance support to ensure the project progress, capital efficiency as well as meeting the electricity demand for socio-economic development of the province.
Author: Phan Anh