Key traffic projects need more than 14 million cubic meters of leveling material
Phan Thiet - Dau Giay expressway project is still short of more than 600 thousand cubic meters of land for embankment
According to the Department of Transport, the demand for leveling materials for four key traffic projects to be implemented in the province in the near future is more than 14 million cubic meters.
Specifically, for the Bien Hoa - Vung Tau expressway project, the demand for leveling materials is 4.8 million cubic meters; ring road 3 project - Ho Chi Minh City, the demand for leveling materials is more than 540 thousand cubic meters; for the ring road 4 project - Ho Chi Minh City, the demand for leveling materials is 4.6 million cubic meters and for the Dau Giay - Tan Phu highway project, the demand for leveling materials is 4.2 million cubic meters.
In addition to the source of leveling materials, these four key traffic projects also need to use nearly 2.6 million cubic meters of construction stone when implemented.
Author: Phan Anh